These easy to follow step-by-step instructions will guide you through every step of the installation process of the SquidGee Dry™ System. Download a PDF version of the SquidGee Dry™ Installation Guide to print out and have beside you when installing the system. (Download the latest version of Adobe Reader)
< Return to Page 1 | Continue to Page 3 >
![]() |
7. SquidGee Dry SealOnce™ Angle cut the tip just under the cone shaped end. This will give the large opening needed for applying SquidGee SealOnce™ to all surfaces. One tube of SquidGee SealOnce™ is needed for each 4 ft 6 inch Main section. |
![]() |
8. Applying SquidGee SealOnce™ It’s very important that you do this step properly. Turn a Main section over and apply a heavy bead of SquidGee SealOnce™ to the bottom. Turn Main section back over and set in place... Press gently! |
![]() |
9. Caulk Floor Joint Caulk the floor joint with enough pressure to force some SquidGee SealOnce™ under the system. |
![]() |
10. Prep By Sanding Surface You will get a much better bond if you use a coarse sandpaper to rough up any vinyl to vinyl surfaces. Do this to both sides of the joining baseboards and the Butt-Joint. |
![]() |
11. Applying Butt-Joints Apply SquidGee SealOnce™ on both sides of the seam. Hook the Butt-Joint at the bottom and snap in place at the top. It’s ok if a Butt-Joint will not snap in place. The floor may not be level or baseboards may not line up. |
![]() |
12. Seal Edges of Butt-Joints Sealing the edges of the Butt-Joints and caulking the bottom will insure there are no leaks. |